Payment terms and milestones in a solar quotation
There is no standard payment schedule, so a quotation should tie each payment to a stage the customer can see, such as order, delivery, installation and commissioning. Write the stages and the amounts in the terms. A scheme subsidy reaches the household afterwards, so the work cannot depend on it.
Last updated
Why payment follows the work
Both sides carry risk. An installer who funds all the equipment before payment takes on the cost, and a customer who pays most of the money before work begins takes on the risk. A schedule tied to visible stages shares the risk and avoids arguments about what has been earned.
These are options an installer can offer, not a standard. The right schedule depends on the size of the job, the supplier's terms and what the customer is willing to accept.
Stages an installer can tie a payment to
Choose the stages that match the job and state each one in plain words.
- On accepting the quotation and placing the order.
- On delivery of the equipment to the site.
- On completion of the installation.
- On commissioning, which for a grid-connected system may depend on the distribution company's steps.
- A held back portion released after commissioning or after a defined period, if both sides agree.
Plan for the subsidy being paid afterwards
Under a scheme such as PM Surya Ghar, the customer pays the installer the full amount and receives the subsidy afterwards, so a quotation should not present the subsidy as a discount on the price. The installer cannot count on the subsidy to fund the work.
Make clear in the terms that the customer pays the quoted amount whatever the subsidy outcome, and that any estimate of the subsidy is indicative.
Put it in writing and track changes
Write the stages, and what the customer receives at each, in the terms and conditions. If the customer changes the system size or equipment, issue a revision and restate the schedule, so the amounts always match the current quotation.
Raise invoices for each stage from your accounting tool, because a quotation is an offer and not a GST invoice.
Where this guide stops
This guide gives no percentages or amounts, because no figure is a standard. Settle them for each job and, for large contracts, have the terms checked by a lawyer.
Step by step
Choose the stages
Pick the stages that match the job, such as order, delivery, installation and commissioning.
Tie each payment to a stage
State what the customer receives at each stage.
Allow for the subsidy
Say that the customer pays the quoted amount and that the subsidy is paid afterwards.
Write it into the terms
Put the schedule in the terms and conditions.
Revise when the job changes
Issue a revision and restate the schedule if the system or equipment changes.
Common mistakes
Presenting the subsidy as a discount
The customer pays in full and receives the subsidy afterwards, so a quotation should not deduct it from the price.
Asking for most of the money before work begins
A schedule weighted to the start moves the risk to the customer and invites disputes.
Leaving the stages vague
A stage that is not described in plain words cannot be checked by either side.
Forgetting to restate the schedule after a change
If the system or equipment changes, the amounts must match the revised quotation.
What to check before you send
- Each payment is tied to a stage the customer can see
- The stages and amounts are written in the terms and conditions
- The quotation says the customer pays the quoted amount whatever the subsidy outcome
- The subsidy is shown as an indicative estimate, not as a discount
- A revision restates the schedule if the system or equipment changes
- Invoices are raised from your accounting tool, not from the quotation
Sources
- MNRE office memorandum on the DCR verification portal, read 10 Oct 2026
Frequently asked questions
What advance should I ask for?
There is no standard. Decide it for the job, tie it to a stage, and write it into the terms. This guide gives no figure.
Can I take payment in stages?
Yes. Tying each payment to a delivered stage is a common way to share the risk, and it should be written into the terms.
Does the customer pay less because of the subsidy?
Not at the time of payment. Under a scheme such as PM Surya Ghar the customer pays in full and receives the subsidy afterwards, so the quotation should say so.
What if the customer changes the system?
Issue a revision and restate the stages and amounts, so the schedule matches the current quotation.
Cite this page
Bharat Solar Venture. "Solar payment terms and milestones." Bharat Solar Venture, last updated 13 Oct 2026. https://bharatsolarventure.in/guides/solar-payment-terms-and-milestones
Canonical URL: https://bharatsolarventure.in/guides/solar-payment-terms-and-milestones
Your next enquiry is waiting
Set your company up once. After that a quotation takes a few minutes, and it already carries your GSTIN, bank details and signature.
Create your account